• Malaysia Rail Link Sdn Bhd (MRL) chief executive officer Datuk Seri Darwis Abdul Razak said the Kota Bharu station, which is under construction, will have multiple platforms and be equipped with parking spaces, pick-up and drop-off locations, covered walkways, workers’ quarters, and a landscape site, among other facilities.

KOTA BHARU (June 23): The construction of the East Coast Railway Link (ECRL) in Kelantan, covering 43 kilometres (km), has reached a progress of 79.81% as of last month, said Malaysia Rail Link Sdn Bhd (MRL) chief executive officer Datuk Seri Darwis Abdul Razak.

He said the progress aligns with the project schedule for the expected completion of the railway line from Kota Bharu to Terminal Bersepadu Gombak (integrated transport terminal).

He said Kelantan would have a passenger station (Kota Bharu station) in Bandar Baru Tunjong, and the Pasir Puteh station in Kampung Cherang Tuli for passengers and cargo.

He mentioned that the Kota Bharu station, which is under construction, will have multiple platforms and be equipped with parking spaces, pick-up and drop-off locations, covered walkways, workers’ quarters, and a landscape site, among other facilities.

He said this in a statement issued in conjunction with the visit by Kelantan Crown Prince Tengku Muhammad Fakhry Petra to the ECRL station site in Bandar Baru Tunjong, here on Sunday.

Darwis said the Kota Bharu station will feature the “Rumah Meleh Melayu” and “Bunga Ketam Guri” design concepts and other unique characteristics of Kelantan culture.

Tengku Muhammad Fakhry was briefed on the project’s progress, before proceeding to the railway site.

Also present were state Public Works, Infrastructure, Water and Rural Development Committee chairman Datuk Dr Izani Husin, and Kelantan police chief Datuk Muhamad Zaki Harun.

Transport Minister Anthony Loke Siew Fook was quoted as saying that he was confident that the ECRL project would be completed according to schedule in December 2026, and operational starting January 2027.

The 665-km ECRL project, costing RM50.27 billion, will connect Kota Bharu with the Gombak integrated transport terminal, cutting travel time to four hours, from seven hours by road or over 12 hours during festive seasons.

Looking to buy a home? Sign up for EdgeProp START and get exclusive rewards and vouchers for ANY home purchase in Malaysia (primary or subsale)!

SHARE
RELATED POSTS
  1. Inaugural Realtors Round Table: A night of celebration and recognition
  2. MRT3 Line: Which stations have the most new property developments?
  3. PGF acquires land in Kulim for new plant set to more than triple capacity